#10 Green Renovation

In late September 2014 we began the renovation process on #10 green.  Over several weeks we were able to enlarge the green and overall change the entire green complex.  Below are pictures and descriptions of the process.

Before                                                                                            After

IMG_0577IMG_0615                                                                                                                          

The process began with the removal of sod and dirt from the left side of the existing green complex.

??????????????????????????????????????????????????????????????

Then re-shaping of the entire area was done.  In doing this we laid out the new dimensions of the green and shelled that area out to a depth of 12 inches.

??????????????????????????????????????????????????????????????

We then added new irrigation as well as new sub surface drainage to the new green area.

??????????????????????????????????????????????????????????????

Once all the infrastructure was installed the new green cavity was filled with stone and sand to match the rootzone of the existing green.  The sand base was then graded, compacted and topped off with sod from #10 green at Loudon Meadows.

??????????????????????????????????????????????????????????????

??????????????????????????????????????????????????????????????